Saturday, 16 November 2013

3 Days to PCI !!!

End week 23: Outdoor painting finished & 3 Days to PCI

Nicely painted façade window details + blinds & flyscreens fitted:

Front door colour details:

Under the front door:

Down Pipes fitted and painted:

New drainage hole:





Saturday, 9 November 2013

Finishing touches

Week 22: Finishing touches!!!

Garage door was fitted, façade started to be painted, temp fences were removed, loo removed and rubbish taken away:

Final 4 corner roof tiles were loose, and this week they were properly affixed.

Side render completely painted:

Garage side door replaced:

Works under the front door:

Toilet fan were fitted:

Garage door from inside:

Painting inspection was carried out. Blue labels means "places to be fixed!"

Carpet started to be fitted but with wrong underlay.... :(

Saturday, 7 September 2013

Fixing Stage finished:

Week 13 - House Rendering, Internal Doors, Kitchen & Vanities, Cornices, Architraves & Skirtings (Fixing Stage Finished):

The house render is looking stunning!
We wanted to get that beautiful render look to the entire house, and for that reason we used Hebel. We were a little in doubt but we decided to take a gamble. We researched a lot the material, we visited several Hebel houses and went for it.
But now that the render is ready to be painted, we are really happy with the outcome. Sincerely, the house looks better than we were expecting.


Kitchen & Living getting shaped:


Laundry:

Bathrooms:



Friday, 16 August 2013

Lock Up Stage finished

Week 10:

All cabling done outside, and some minor aesthetic feature:


 Left side completed Hebel view:

Back side completed Hebel view:

Right side completed Hebel view:

Wet areas in floor showers done:


 And also all cabling done inside.
 
 Evaporative cooling system ducts installed.

Heater and ducts installed.


Monday, 5 August 2013

Lock Up stage (cont...)

Week 9:

"Lock Up" stage continues with more Hebel walls placed.

The Hebel in the back of the house is nearly finished, just needing some minor touches here and there.



And one of the sides of the house is also nearly finished, just waiting for minor touches.

While on the other side of the house, Hebel walls are getting screwed into the metal frames.

Saturday, 3 August 2013

Hebel starts

End of Week 8:

House Façade on Saturday:

House Façade on Thursday:

Backyard on Saturday:

Backyard on Thursday: