Week 23: PCI booked, Carpet, Painting and Termite Protection
Façade got a little more painting done, but bad weather is delaying it to be fully painted:
Wrong underlay was changed. Now carpet feels really soft and nice.
Hallway carpet fitted:
Lounge carpet fitted:
Master bedroom carpet fitted:
Ensuite got a couple of spot lights to replace our mirror light that didn't fit in there:
Carpet fitted, Walk-In-Robe (Hers):
And also, carpet fitted on Walk-In-Robe (His):
Termite Protection System fitted:
Showing posts with label Painting. Show all posts
Showing posts with label Painting. Show all posts
Friday, 15 November 2013
Saturday, 9 November 2013
Finishing touches
Week 22: Finishing touches!!!
Garage door was fitted, façade started to be painted, temp fences were removed, loo removed and rubbish taken away:
Final 4 corner roof tiles were loose, and this week they were properly affixed.
Side render completely painted:
Garage side door replaced:
Works under the front door:
Toilet fan were fitted:
Garage door from inside:
Painting inspection was carried out. Blue labels means "places to be fixed!"
Carpet started to be fitted but with wrong underlay.... :(
Garage door was fitted, façade started to be painted, temp fences were removed, loo removed and rubbish taken away:
Final 4 corner roof tiles were loose, and this week they were properly affixed.
Side render completely painted:
Garage side door replaced:
Works under the front door:
Toilet fan were fitted:
Garage door from inside:
Painting inspection was carried out. Blue labels means "places to be fixed!"
Carpet started to be fitted but with wrong underlay.... :(
Saturday, 12 October 2013
Outdoor Ceiling Painting, Pantry and Shelves
Week 18: Outdoor ceiling, Pantry and wardrobes' shelves fitted
Outdoor painting started. Ceiling got painted around the house. The alfresco is looking amazing now!!!
Pantry shelves were fitted.
Wardrobes got fitted:
Walk in Robes also got fitted:
And tiles arrived..... next week will be a busy one!!!!
Outdoor painting started. Ceiling got painted around the house. The alfresco is looking amazing now!!!
Pantry shelves were fitted.
Wardrobes got fitted:
Walk in Robes also got fitted:
And tiles arrived..... next week will be a busy one!!!!
Tuesday, 1 October 2013
House Interior Painting Finished
Week 17: (House Interior Painting Finished)
Waterproofing coating on bathroom walls:
First sight of our external charcoal feature colour for doors and facade feature wall:
Garage also painted, now just waiting for neighbour to finish building his brick walls, so we can get our render painted:
Waterproofing coating on bathroom walls:
First sight of our external charcoal feature colour for doors and facade feature wall:
Garage also painted, now just waiting for neighbour to finish building his brick walls, so we can get our render painted:
Monday, 30 September 2013
Painting Starts
End of Week 16 (Painting starts):
I was driving pass the house on Friday, when I noticed that the garage door was missing, so I stopped to have a look what was going on. And for my surprise, the house was been painted. Very nice surprise as I was expecting it just to happen on the following week.
I was driving pass the house on Friday, when I noticed that the garage door was missing, so I stopped to have a look what was going on. And for my surprise, the house was been painted. Very nice surprise as I was expecting it just to happen on the following week.