Week 24: Practical Completion Inspection
163 days after the commencement of the house construction we had our PCI.
We bought a House & Land package off-the-plan and it was a 13 months wait to see our dream home finally ready.
So, it was a rather exciting and happy day for us.
We had met the Site Supervisor 5 weeks ago and we had already told him all our concerns, and they were all attended to.
PCI was pretty smooth and just a few items will need attention.
We were too busy though going around the house and checking everything, so no pictures were taken.
The items that still need attention are:
- Connect stormwater to downpipe @ front porch.
- Paint touch ups as per blue stickers (about 20 spots).
- Paint underside of mould to front façade.
- Missing grout floor in pantry (2 spots)
- Fit off Heating/Cooling
- Install all feature light fittings
- Install GPO for alarm box
Handover will be in a week time and we are looking forward to be on our home soon.
Showing posts with label PCI. Show all posts
Showing posts with label PCI. Show all posts
Wednesday, 20 November 2013
Saturday, 16 November 2013
3 Days to PCI !!!
End week 23: Outdoor painting finished & 3 Days to PCI
Nicely painted façade window details + blinds & flyscreens fitted:
Front door colour details:
Under the front door:
Down Pipes fitted and painted:
New drainage hole:
Nicely painted façade window details + blinds & flyscreens fitted:
Front door colour details:
Under the front door:
Down Pipes fitted and painted:
New drainage hole:
Friday, 15 November 2013
Final Week Before PCI
Week 23: PCI booked, Carpet, Painting and Termite Protection
Façade got a little more painting done, but bad weather is delaying it to be fully painted:
Wrong underlay was changed. Now carpet feels really soft and nice.
Hallway carpet fitted:
Lounge carpet fitted:
Master bedroom carpet fitted:
Ensuite got a couple of spot lights to replace our mirror light that didn't fit in there:
Carpet fitted, Walk-In-Robe (Hers):
And also, carpet fitted on Walk-In-Robe (His):
Termite Protection System fitted:
Façade got a little more painting done, but bad weather is delaying it to be fully painted:
Wrong underlay was changed. Now carpet feels really soft and nice.
Hallway carpet fitted:
Lounge carpet fitted:
Master bedroom carpet fitted:
Ensuite got a couple of spot lights to replace our mirror light that didn't fit in there:
Carpet fitted, Walk-In-Robe (Hers):
And also, carpet fitted on Walk-In-Robe (His):
Termite Protection System fitted: