Monday, 15 July 2013

Work Begins





Week 1 & 2:
Land was scraped and loose surface fill, roots and vegetation was removed.
Block received temp fencing, water main connection, a portable loo and a metal cage for disposal of materials.

Week 3:
More excavation, plumbing connections and pipes were laid, electricity connection and power box installed.

Week 4:
Crushed rock were laid on the block. And lots of rain!!!


 
 
Week 4:
Slab material arrived.