Wednesday, 31 July 2013

House Wrap

Week 8 (cont...)

House completely wrapped and solar heating installed.



 
 
 

Tuesday, 30 July 2013

Roof

Week 8:

Roof, day 2:


 


Roof, day 1:





 
 

Friday, 26 July 2013

Gutters and Hot & Cold water

End of week 7:
 
Gutter installed.

Hot and Cold water to toilets and kitchen connected.
 
 

Thursday, 25 July 2013

Frame Stage

 
Mid Week 7:
 
Frame: 



 



Frame Stage begins, day 1:



 
 

Thursday, 18 July 2013

Slab Stage

Week 6:

Slab framed and ready to be poured.




















Following day:

Slab finished





Monday, 15 July 2013

Work Begins





Week 1 & 2:
Land was scraped and loose surface fill, roots and vegetation was removed.
Block received temp fencing, water main connection, a portable loo and a metal cage for disposal of materials.

Week 3:
More excavation, plumbing connections and pipes were laid, electricity connection and power box installed.

Week 4:
Crushed rock were laid on the block. And lots of rain!!!


 
 
Week 4:
Slab material arrived.