House completely wrapped and solar heating installed.
Wednesday, 31 July 2013
Tuesday, 30 July 2013
Friday, 26 July 2013
Thursday, 25 July 2013
Thursday, 18 July 2013
Monday, 15 July 2013
Work Begins
Week 1 & 2:
Land was scraped and loose surface fill, roots and vegetation was removed.
Block received temp fencing, water main connection, a portable loo and a metal cage for disposal of materials.
Week 3:
More excavation, plumbing connections and pipes were laid, electricity connection and power box installed.
Week 4:
Crushed rock were laid on the block. And lots of rain!!!
Week 4:
Slab material arrived.