Week 24: Practical Completion Inspection
163 days after the commencement of the house construction we had our PCI.
We bought a House & Land package off-the-plan and it was a 13 months wait to see our dream home finally ready.
So, it was a rather exciting and happy day for us.
We had met the Site Supervisor 5 weeks ago and we had already told him all our concerns, and they were all attended to.
PCI was pretty smooth and just a few items will need attention.
We were too busy though going around the house and checking everything, so no pictures were taken.
The items that still need attention are:
- Connect stormwater to downpipe @ front porch.
- Paint touch ups as per blue stickers (about 20 spots).
- Paint underside of mould to front façade.
- Missing grout floor in pantry (2 spots)
- Fit off Heating/Cooling
- Install all feature light fittings
- Install GPO for alarm box
Handover will be in a week time and we are looking forward to be on our home soon.
Wednesday, 20 November 2013
Saturday, 16 November 2013
3 Days to PCI !!!
End week 23: Outdoor painting finished & 3 Days to PCI
Nicely painted façade window details + blinds & flyscreens fitted:
Front door colour details:
Under the front door:
Down Pipes fitted and painted:
New drainage hole:
Nicely painted façade window details + blinds & flyscreens fitted:
Front door colour details:
Under the front door:
Down Pipes fitted and painted:
New drainage hole:
Friday, 15 November 2013
Final Week Before PCI
Week 23: PCI booked, Carpet, Painting and Termite Protection
Façade got a little more painting done, but bad weather is delaying it to be fully painted:
Wrong underlay was changed. Now carpet feels really soft and nice.
Hallway carpet fitted:
Lounge carpet fitted:
Master bedroom carpet fitted:
Ensuite got a couple of spot lights to replace our mirror light that didn't fit in there:
Carpet fitted, Walk-In-Robe (Hers):
And also, carpet fitted on Walk-In-Robe (His):
Termite Protection System fitted:
Façade got a little more painting done, but bad weather is delaying it to be fully painted:
Wrong underlay was changed. Now carpet feels really soft and nice.
Hallway carpet fitted:
Lounge carpet fitted:
Master bedroom carpet fitted:
Ensuite got a couple of spot lights to replace our mirror light that didn't fit in there:
Carpet fitted, Walk-In-Robe (Hers):
And also, carpet fitted on Walk-In-Robe (His):
Termite Protection System fitted:
Saturday, 9 November 2013
Finishing touches
Week 22: Finishing touches!!!
Garage door was fitted, façade started to be painted, temp fences were removed, loo removed and rubbish taken away:
Final 4 corner roof tiles were loose, and this week they were properly affixed.
Side render completely painted:
Garage side door replaced:
Works under the front door:
Toilet fan were fitted:
Garage door from inside:
Painting inspection was carried out. Blue labels means "places to be fixed!"
Carpet started to be fitted but with wrong underlay.... :(
Garage door was fitted, façade started to be painted, temp fences were removed, loo removed and rubbish taken away:
Final 4 corner roof tiles were loose, and this week they were properly affixed.
Side render completely painted:
Garage side door replaced:
Works under the front door:
Toilet fan were fitted:
Garage door from inside:
Painting inspection was carried out. Blue labels means "places to be fixed!"
Carpet started to be fitted but with wrong underlay.... :(
Wednesday, 30 October 2013
Kitchen, Laundry, Toilets, Bathrooms and Doors
Week 21: Kitchen, Laundry, Toilets, Bathrooms and Doors
Ensuite has been fully fitted and is finished:
Bath fitted on bathroom:
Showers fitted on ensuite and bathroom:
Toilet fitted:
Splashback:
Sink and shower head, we have placed a cardboard next to it, so it CANNOT be seen from outside.... lets see how long it lasts.... :(
Laundry finished and fully fitted:
Door handles fitted:
Wardrobe handles also fitted:
Pantry's sliding door handle:
Doorstoppers fitted:
And the best news of the week...."We got light!!!"
Ensuite has been fully fitted and is finished:
Bath fitted on bathroom:
Showers fitted on ensuite and bathroom:
Toilet fitted:
Splashback:
Sink and shower head, we have placed a cardboard next to it, so it CANNOT be seen from outside.... lets see how long it lasts.... :(
Laundry finished and fully fitted:
Door handles fitted:
Wardrobe handles also fitted:
Pantry's sliding door handle:
Doorstoppers fitted:
And the best news of the week...."We got light!!!"
Friday, 25 October 2013
Bits and Pieces
Week 20: Shower Screen, Power Sockets, Light Switches, Data, Telephone and TV Points
Ensuite received mirrors and shower screen:
Bathroom mirror:
Bathroom shower screen:
Bathroom tile details:
Power sockets, light switches, data points and tv points were installed:
Ensuite received mirrors and shower screen:
Bathroom mirror:
Bathroom shower screen:
Bathroom tile details:
Power sockets, light switches, data points and tv points were installed:
Saturday, 19 October 2013
Tiling Starts
Week 19: Tiling Starts
Hallway - day 3:
Roompus - day 3:
Bathroom - day 2:
Hallway - day 2:
Living - day 1:
Roompus - day 1:
Laundry - day 1:
Bathroom:
Toilet:
Stacks of tiles everywhere:
Hallway - day 3:
Roompus - day 3:
Bathroom - day 2:
Hallway - day 2:
Living - day 1:
Roompus - day 1:
Laundry - day 1:
Bathroom:
Toilet:
Stacks of tiles everywhere: